← Back to the blog
By RenewaNews · Tuesday, September 29, 2026 · 5 min read

Solar's Declining Upfront Capital Intensity Is Changing How Developers Structure PPAs and Balance Sheets

Hero image for the article “Solar's Declining Upfront Capital Intensity Is Changing How Developers Structure PPAs and Balance Sheets”

Original illustration created for RenewaNews.

Sponsored
AI-Driven Interactive Websites

Scatec's second-quarter 2024 presentation, published July 18, 2024, shows PPA terms in its South Africa and Brazil pipeline shortening to 10–15 years from the traditional 20–25, while debt service coverage ratios hold steady. CEO Terje Pilskog calls it a "capital-light" strategy that leverages declining solar component prices to lift equity IRRs. Scatec's disclosure does not state the coverage ratio itself, only that it holds; what it does show is a pipeline being resized around lower capital intensity rather than around the longer contract tenors that project debt historically demanded.

Adani Green Energy is making a comparable move in a market built on the opposite assumption. The company's July 25, 2024 investor presentation attributes a change in the capital structure of its Khavda renewable energy park to "economies of scale and declining solar costs," and says a reduction in equity required per megawatt for new solar starts — a reduction it does not quantify — is enabling a "merchant-heavy" strategy across a portion of its pipeline, a departure from the 25-year fixed-price PPAs that have anchored Indian solar finance since the National Solar Mission.

That is a notable reversal for a market where long-tenor fixed-price contracts have been the default financing mechanism for a decade. If a developer with Adani's balance sheet is willing to carry merchant exposure on new capacity because the equity check per megawatt has shrunk, smaller developers without investment-grade backing will face pressure to follow or to accept financing terms priced against that new baseline.

What is actually driving the tenor shift

The global weighted average installed cost of utility-scale solar PV fell 12% in 2023 to $758 per kilowatt, according to IRENA's Renewable Power Generation Costs in 2023 report, published September 24, 2024 — 86% below 2010 levels. IRENA Director-General Francesco La Camera says solar PV "is now significantly undercutting fossil fuel alternatives on a total lifecycle cost basis," with the agency putting global weighted average solar LCOE at $0.044/kWh.

Lazard's Levelized Cost of Energy+ analysis, published June 1, 2024, puts unsubsidized utility-scale solar capex at $700–$1,400/kW against $1,000–$1,300/kW for combined-cycle gas. Lazard's own capacity-factor adjustment does not go as far as saying solar's per-unit-of-output capital requirement now beats gas outright; the report's language is that lower solar capex "offsets" the capacity-factor gap, narrowing it rather than closing it. The tenor compression at Scatec and the merchant push at Adani are better read as company-level financing decisions than as evidence that Lazard has declared a crossover — Lazard hasn't.

Where the industry says the threshold has already been crossed

Ember's Global Electricity Review 2024, published May 8, 2024, found that in many markets the upfront capital needed to build enough solar capacity to match a coal plant's annual output has fallen below the cost of the coal plant itself. Ember identifies this shift as a driver of accelerating project pipelines in emerging economies.

BloombergNEF is more specific about geography. BNEF analysts say the "capital intensity threshold" has been crossed in Chile, Australia and parts of the Middle East, where solar now requires less upfront capital per MWh of expected annual generation than any fossil fuel alternative, according to its 2024 Renewable Energy Outlook: High Irradiance Markets, published July 10, 2024.

NextEra is pricing the same shift, without disclosing the number

NextEra Energy Resources made a parallel case at its June 11, 2024 investor conference presentation, listing "Capital Intensity" as a named metric in its 2024–2027 outlook. The presentation states that declining solar capex allows for "superior returns" even as PPA prices stabilize or decline, and it describes a reduction in project-level debt required per megawatt without disclosing the size of that reduction. NextEra links that lower debt sizing to more flexible PPA tenors and a higher share of merchant-tail revenue in its financing structures — meaning a growing portion of expected cash flow is left unhedged against future power prices rather than locked into a long-dated offtake.

Why gas can't match the new pricing

PV Tech's August 14, 2024 analysis of PPA pricing describes the offtake side of the same mechanism. Because capex is the dominant cost driver for a solar project, the outlet reports a 15–20% drop in module and hardware costs allowed developers to price PPAs aggressively enough to break the historical correlation between gas prices and solar contract rates. Gas-fired generation, dependent on fuel costs that move independently of the capital markets, cannot match that pricing even when gas itself is cheap.

The IEA's World Energy Investment 2024, published June 1, 2024, frames the same dynamic at the portfolio level. The agency reports that for every dollar invested in fossil fuels today, nearly two dollars are going into clean energy, attributing the split to solar's "compelling economics." The IEA notes that lower unit capital costs are letting developers absorb higher financing costs without raising PPA strike prices — the mechanism linking a global capex statistic to a negotiating position in a specific offtake contract.

What lenders are actually underwriting

Lower total capex per megawatt shrinks the absolute debt principal a lender is underwriting, which is what lets BNEF's high-irradiance markets support shorter tenors without breaching coverage ratios. It also changes what a shorter PPA costs the sponsor in flexibility: Scatec's move to 10–15 year contracts and NextEra's growing merchant-tail share both depend on the premise that capital at risk per unit of output has fallen far enough to justify carrying uncontracted price exposure on part of the asset's life.

None of the disclosures reviewed here quantify how much merchant exposure a lender will accept before repricing debt, and none address what happens to these structures if merchant capture prices in Gujarat or the Atacama fall further than sponsors have assumed.

Links Verified at Time of Publish

Sources

This article was reported from the following sources.

  1. Renewable Power Generation Costs in 2023 — International Renewable Energy Agency (IRENA), 2024-09-24
  2. Global Electricity Review 2024 — Ember, 2024-05-08
  3. NextEra Energy 2024 Investor Conference Presentation — NextEra Energy, Inc., 2024-06-11
  4. Levelized Cost of Energy+ (LCOE 17.0) — Lazard, 2024-06-01
  5. World Energy Investment 2024 — International Energy Agency (IEA), 2024-06-01
  6. Solar PPA prices are decoupling from gas: Here's why — PV Tech, 2024-08-14
  7. 2024 Renewable Energy Outlook: High Irradiance Markets — BloombergNEF (BNEF), 2024-07-10
Sponsored
Newsletters Automation & Hosting Platform

More from the blog